Road Construction Updates

Below you will find 2022 road construction and infrastructure projects planned in the Town of Quispamsis. Click on each “Type” for more information on detours, maps, contacts, etc. for individual projects. Please be cautious of workers and equipment while travelling through these areas. We appreciate your understanding and cooperation while this work is being completed.

Project Type Duration Current Work Description Updated

Street Upgrades







 

12 Weeks The general contractor, Debly Enterprises Ltd. is continuing the Street Upgrading 2022 project. The majority of streets have been paved with the exception of Old Coach Rd and Hammond River Park Access Road. Landscaping shall follow. Old Coach Road paving will occur once the sidewalk is completed.

Driveways on majority of streets should now be complete.
September 22, 2022

Water Main System Old Coach Road

12 Weeks The Town’s contractor MIDI Construction Ltd. is continuing the Old Coach Road project. Curb has been installed with sidewalk to be poured next week. Landscaping is underway. September 22, 2022

Meenans Cove Road Upgrades

 

8 weeks

The general contractor, Debly Enterprises Ltd. is continuing the Street Upgrading 2022 project. The Meenans Cove Road project is nearing completion with seal and base asphalt complete. Shouldering is complete and landscaping shall follow. Deficiencies are being addressed.

September 22, 2022

Drainage Improvements

 

8 Weeks

Work will be completed on Alderbrook and Forresters Cove Road. For the up coming week.

August 31, 2022