Road Construction Updates

Below you will find 2019 road construction and infrastructure projects planned in the Town of Quispamsis. Click on each “Type” for more information on detours, maps, contacts, etc. for individual projects. Please be cautious of workers and equipment while travelling through these areas. We appreciate your understanding and cooperation while this work is being completed.

Letter To Residents Regarding 2019 Street Capital Upgrading

Project Type Duration Current Work Description Updated
Storm Drainage Improvements 4 Weeks The contractor, Steele Trucking Ltd. will continue to work on the 2019 Drainage Improvements project. Work will be done on  Gondola Point Road, Hammond River Road, Old Coach Road, Cedar Grove Drive, Meenans Cove Road, and Stoneyplain Avenue. June 21, 2019
Gondola Boulevard Phase 3

 

Detour Plan

6 Weeks MIDI Construction will be continuing the Gondola Boulevard Corridor Improvements next week.  Storm pipe and catchbasins have been installed.  Full roadway reconstruction from Saunders Drive to Marianne Crescent is complete.  Storm sewer will will commence at Marianne with ditching to civic #104.  Asphalt preparations may also begin this week.  The Town’s contractor will also be detouring traffic on Gondola Blvd as per the attached detour plan.  Work is occurring at the intersection of Marianne and Gondola Blvd near civic 128. This work is scheduled on Tuesday Sept. 24 and should be complete by end of day Wednesday Sept. 25.

 

September 20, 2019

Hampton Road Watermain

 

1-2 Weeks Fairville Construction Ltd. have completed of the installation of the watermain along Hampton Road.   Pressure testing has been successful.  Curb, gutter and sidewalk construction is complete. Landscaping shall continue next week.  Asphalt base installation is partially complete with seal scheduled for this week by Debly Enterprises.  Line work and striping will begin upon completion of seal asphalt. September 20, 2019
Street Upgrades 3-4 Weeks The general contractor, Debly Enterprises Ltd. are continuing the Street Upgrading 2019 project.  Quispamsis Rd and French Village Rd will have ditching and culverts installed this week. Melanie to have seal placed. Morach will have shouldering and landscaping placed. The public should be aware of reduced speed limits throughout construction zones. September 20, 2019